5.2. Commissioning the Preheat
5.2.1. Functional Testing Field Tips
Key Commissioning Test Requirements
5.3. Testing Guidance and Sample Test Forms
Figure 5.1: Make-Up Air Handling Unit with Preheat and Reheat Coils
This chapter focuses on heating elements that are in the preheat position in an air handling unit. Preheat elements are the first element in the air stream following the intake and prefilter, which is a position that allows them to protect the rest of the system and building from freezing air. Frequently, this heating element is a coil that uses steam, hot water, or electricity as an energy source. In some situations, the heating element is a fossil fuel fired furnace or an energy recovery coil.
From a psychrometric and HVAC process standpoint, not all heating elements are the same. The specific function they provide depends on:
· The location of the coil in the system relative to other components.
· The manner in which the coil is connected to its supply of heating energy (to prevent freezing).
· The manner in which the coil is controlled.
If the preheat element is to successfully provide the intended function, it is critical that these issues be taken into consideration when the system is configured and the heating element is selected and connected. Failure to do so can result in, at a minimum, the inability to provide the required level of performance and, in the worst case, can damage coils and building elements due to freezing.
The differences between preheat, reheat, warm-up, and heating processes in the air handling unit are also emphasized in this chapter. Many heating elements are labeled as preheat elements, but not all of them are properly configured to perform that function reliably. Preheat is required by an air handling system if it will see operating conditions that will result in supply temperatures that:
· Are lower than required to maintain the design conditions at the load served.
· Will subject the system, its components, and/or the loads served to air at subfreezing temperatures and thereby cause damage by freezing.
True preheat applications are typically found on 100% outdoor air systems and on systems with high outdoor air fractions relative to their total supply flow. Unless they are located in an extreme environment, most air handling systems serving office environments will seldom require preheat if their minimum outside air percentage is 20-30% of the supply flow rate and good mixing is achieved. In Section 3.1.2, a discussion on the relationship between minimum outside air and preheat illustrates this concept.
Generally, for 100% outdoor air systems, the coil inlet conditions are set by the worst-case outdoor conditions on record for the area. For recirculating systems, the coil inlet conditions are based on the worst-case mixed air conditions (the maximum anticipated minimum outdoor air requirement and the minimum anticipated return air temperature).
The preceding paragraph made reference to the worst-case outdoor conditions on record for the area. It is important to recognize that these conditions may be significantly different than the heating design conditions for the area. Notice that the ASHRAE 99% design numbers are exceeded for 1% of the hours in a year (about 90 hours). There are some locations where the design condition is above freezing but temperatures occasionally fall below freezing. A design based on the design values would presume that the installation did not have to deal with subfreezing air. The reality of the situation, as represented by the extremes, is that the system would in fact see subfreezing temperatures. A design that did not reflect this contingency could experience significant operating problems or even failures when the subfreezing weather occurred. These problems will be a nuisance in most cases and could be crippling to some facilities serving critical health care or production loads.
In contrast to preheat elements, heating elements that are located downstream of the air handling system’s cooling coils are referred to as being in the reheat position. The summertime cooling coil discharge temperature is typically set based on the amount of dehumidification required to achieve adequate dehumidification for the occupied zone (see Chapter 6: Cooling). The required volume of air, when supplied at this temperature, can overcool the occupied zone under some load conditions. Typically, overcooling can occur in situations where the flow to the occupied zone is set based on air change requirements, ventilation requirements, or make-up air requirements rather than being set by space sensible gains and temperature requirements. Clean rooms and hospital surgeries are good examples of applications where this can occur due to the high air change rates associated with maintaining cleanliness. In these situations, the reheat coil is used to warm the discharge air off the cooling coil as necessary to prevent overcooling of the space while still maintaining the required air flow and space humidity condition. Reheat is an energy-intensive process since it is intentional simultaneous heating and cooling. These functions are discussed in greater detail in Chapter 8: Reheat and are mentioned here in order to distinguish the preheat process from the reheat process. Figure 5.1 illustrates a system that has both a preheat coil and a reheat coil.
Figure 5.1: Make-Up Air Handling Unit with Preheat and Reheat Coils
This 100% outdoor air unit has both a preheat and a reheat coil. The preheat coil first raises the temperature of the air sufficiently to protect the rest of the unit and the area served from sub-freezing temperatures. The integral face and bypass design allows the coil to handle sub-freezing air without danger of freezing the condensate. The reheat coil is located after the cooling coil. The cooling coil discharge temperature is set to deliver saturated air with a specific humidity level as required to maintain the space humidity conditions in the summer. Since the air may overcool the space, the reheat coil warms the air as necessary. Either coil could provide a warm-up function, although it would be an energy intensive process given the system brings in 100% outdoor air.

Some system designs provide the reheat function at the zone location rather than at the central system location. This allows the reheat process to be limited to only the areas requiring it due to the specific needs of the zone while optimizing the central system supply temperature based on the needs of the critical zone.
Systems can also provide the reheat function at both the zone and the central system. Zone reheat coils are often installed in air handling systems that serve a mix of interior and perimeter zones. While the terminal units associated with the perimeter and interior applications are often physically identical and controlled by identical control sequences, there are significant HVAC process differences that need to be considered, since interior zones reheat, but unlike perimeter zones, never have net loss of heat (heating load).
Heating elements located in either the preheat or reheat position can be used for heating in instances where the losses from the zone exceed the internal gains. In this case, the energy that is put into the heating element is used to offset energy losses from the space - a true space heating application. Contrast this with preheat elements, where the energy is required to warm up outdoor air, or reheat elements, where the energy is required to control the HVAC process as necessary to hit the target conditions in the occupied zone. Similarly, elements in either preheat or reheat location can provide the warm-up function often required when a scheduled air handling system is shut down during unoccupied periods and the outdoor conditions result in a net loss of energy from the space.
Many air handling systems will have preheat, reheat, heating, and warm-up requirements for some portion of their operating cycle. Consider the following. If you improved the insulation on the area served by the air handling system, you might lower or even eliminate the heating and warm-up requirements associated with a net energy loss from the space. However, the insulation would not eliminate the preheat requirements or the reheat requirements (although it may modify them) unless you changed the airflow and/or humidity requirements for the zone. These are subtle but important distinctions because the different functions require different control strategies.
Verifying the proper control sequence for preheat elements is an important aspect of commissioning. Table 5.1 contrasts the preheat, reheat, heating, and warm-up processes, summarizing the information in the preceding paragraphs.
|
|
Preheat |
Reheat |
Heating |
Warm-up |
|
Function |
Offset heating requirements associated with ventilation and make-up air; protect the system and building from sub-freezing air. |
Offset unnecessary sensible cooling that was done to provide dehumidification to meet the space design requirement. |
Offset space sensible losses through the building envelope associated with the rate of heat transfer exceeding the rate of heat gain in the perimeter zone. |
Similar to the heating coil but also must pick up the accumulated loads that occur as the building and its contents cool off during the unoccupied cycle. |
|
Load Offset by Heating Energy |
Make up and ventilation air heating load |
False cooling load |
Perimeter heating and infiltration loads |
Accumulated perimeter heating and infiltration loads |
|
Location |
First element after the intake for 100% outdoor air systems; first after the mixing box for recirculating systems |
After the cooling coil. |
Not critical but first after the mixing plenum provides some measure of protection for the rest of the system. |
Not critical but first after the mixing plenum provides some measure of protection for the rest of the system. |
|
Installation |
Configure to handle air at subfreezing temperatures.2 |
None that is special to the function. |
None that is special to the function. |
None that is special to the function. |
|
Control |
Controlled to maintain a safe (above freezing) leaving air condition under all operating modes and sequenced with other elements to avoid energy waste. The freezestat must be downstream of the preheat coil if it will see sub freezing entering air temperatures. |
The cooling coil discharge temperature setpoint is selected based on design humidity requirements3, while the reheat coil is controlled based on space temperature requirements. The freezestat must be upstream since the reheat coil would not typically be configured for subfreezing air. |
Sequence with other system functions to prevent simultaneous heating and cooling and to prevent using heating when the system is not on minimum outdoor air. The freezestat must be upstream since the coil would not typically be configured for subfreezing air. |
Sequence with other system functions to prevent simultaneous heating and cooling and to prevent using outdoor air during the warm-up cycle. The freezestat must be upstream since the coil would not typically be configured for subfreezing air. |
Notes:
1. Heat transfer elements should always be located downstream of the first set of prefilters in order to protect them from atmospheric dust and dirt and/or dust and dirt returned from the area served.
2. Occasionally, in a moderate environment, preheat is required due to high ventilation rates but the ambient conditions and return air conditions are such that the entering air temperature to the preheat coil will never be below freezing under any condition.
3. In a climate with very low humidity, the cooling coil discharge temperature setpoint may be selected based on temperature requirements, not humidity.
The following sections present benefits, practical tips, and design issues associated with commissioning an air handler’s preheat section.
Click the button below to access all publicly-available prefunctional checklists, functional test procedures, and test guidance documents referenced in the Testing Guidance and Sample Test Forms table of the Air Handler system module.
Applying the wrong control strategy to the preheat coil can easily produce the desired occupant comfort, but at a significant energy or process control penalty. For example, an economizer-equipped system should be controlled to drive to minimum outdoor air in an effort to maintain discharge set point before the preheat or heating coil is allowed to become active. Failing to ensure this sequencing and simply controlling for a fixed heating coil discharge temperature could result in a significant amount of unnecessary preheat energy consumption. The system would be heating outside air that is actually being brought in for cooling purposes if the economizer is not positioned to minimum outdoor air prior to heating the mixed air stream.
The impact of a misapplied heating coil sequence can ripple out through the rest of the system. A heating coil that was controlled as if it were a reheat coil (based on space temperature and not sequenced with the cooling coil), in an application where reheat was not necessary, could waste an enormous amount of energy due to unnecessary simultaneous heating and cooling. On a VAV system, this effect could ripple out into the fan energy consumption profile if the system supply temperature was raised enough to cause the terminal equipment to demand more flow than was necessary to satisfy the loads.
In contrast, a reheat coil that was controlled in sequence with the cooling coil and economizer dampers (as if it were a heating coil) probably would save energy but at the cost of losing control of the desired space design conditions. Sequencing the reheat function with the other air handling system functions would most likely result in space humidity conditions that were above the required specification. This deviation for the design humidity requirement could have an impact on IAQ, product quality, occupant comfort, and may even result in conditions that degrade the building structural and architectural elements